

Invest. Improve. Innovate.
About
Infrastructure Plan
Five years ago, the City Council approved an Infrastructure Plan that initially included nine projects including a new public safety building, two parking garages, two fire stations and a bike and pedestrian plan, among other projects. Since then, the mix of projects has shifted slightly with the Council pressing the “pause” button on the downtown parking garage and a necessary redesign of future bike boulevards.
The cost of the plan has also significantly gone up with escalating construction costs and changes to the scope of projects. In addition, salaries and benefits of staff working on projects are now budgeted within individual capital projects to more accurately account for the total cost of each project. The current planned cost of the Infrastructure Plan is now $255 million.

PROJECT
COSTS
In June 2014, Palo Alto City Council adopted the Infrastructure Plan that prioritized unfunded projects and identified potential sources of revenue. Included in the plan are nine key projects with the majority of funding coming from an increase in the Transient Occupancy Tax (hotel tax) from 12 to 14 percent that was approved by more than 76 percent of Palo Alto voters in November 2014. Additional funding sources for these infrastructure projects come from the City’s Capital Fund, the Stanford Hospital development agreement, parking in-lieu fees, parks development impact fees, and state grants.
Projects
The City is in the process of designing and building the nine infrastructure projects identified by Council. A couple are complete, a few are near completion, and more are on their way. Read up on each project to learn more about the status and background of the project.
Public Safety Building
Building to meet the public safety needs of the community.
Design Start
Jan. 2017
Design End
Sept. 2020
Construction Start
Construction End
Mar. 2021
Fall 2023
Charleston/Arastradero Corridor
Providing safe and reliable access to the corridor.
Design Start
Jan. 2017
Design End
June 2019
Construction Start
Construction End
June 2018
Fall 2022
Fire Station No. 4
Meeting the needs of tomorrow with a new seismically sound fire station.
Design Start
June 2023
Design End
Feb. 2024
Construction Start
Construction End
Apr. 2024
Fall 2025
Byxbee Park
Repurposing landfill and providing open space and hiking trails.
Design Start
Sept. 2023
Design End
Aug. 2024
Construction Start
Construction End
Sept. 2024
Aug. 2025
Highway 101 Bike Bridge
Connecting Palo Alto to the baylands year round.
Design Start
Jan. 2017
Design End
Dec. 2019
Construction Start
Construction End
Jan. 2020
Nov. 2021
California Avenue Garage
Mitigating parking challenges in the Cal. Ave. area.
Design Start
Jan. 2017
Design End
Dec. 2018
Construction Start
Construction End
Jan. 2019
Dec. 2020
Bike/Pedestrian Plan
Expanding bike and walking infrastructure.
Design Start
Jan. 2017
Design End
Jul. 2017
Construction Start
Construction End
Aug. 2017
Project Complete
Fire Station No. 3
Replacing the aging and unsound Fire Station No. 3.
Design Start
Jan. 2016
Design End
Aug. 2017
Construction Start
Construction End
Jan. 2018
Mar. 2020
Downtown Parking Garage
Addressing parking and traffic congestion in the Downtown Area.
Design Start
Jan. 2017
Design End
On hold.
Construction Start
Construction End
On hold.
On hold.
Making Progress
Over the past year or so, there has been a lot of progress on the Infrastructure Plan including:
-
Construction of Fire Station No. 3 was completed in March 2020.
-
Construction of the 627 space California Avenue parking garage is underway. Council has approved the design for the new Public Safety Building, and construction will begin in early 2021.
-
The Charleston/Arastradero Corridor project will see three milestones this fall with scheduled completion of phases 1 and 2 and bid opening for phase 3.
-
The Highway 101 Pedestrian/Bike Bridge construction begins in January 2020 and is anticipated to be completed in summer 2021.
-
Council has pushed “pause” on the downtown parking garage for now and staff plans to bring forward a potential parking guidance system as part of the 2020 budget process as a near term solution.
-
In late 2018, the Council approved the design of the new Public Safety Building that will start construction following the completion of the California Avenue parking structure.